Operation; Inspection Of Installation; Installation Record - Pacific Power Source MS SERIES Operation Manual

Table of Contents

Advertisement

SECTION 4
4.0

OPERATION

4.1

INSPECTION OF INSTALLATION

Inspection of the installation is a very important step prior to operation of the MS-
Series AC Power Source. This is done as a safety measure to prevent injury to
personnel or damage to equipment. Before the cabinet is first turned on, the
wiring and distribution system should be checked. Input and output wiring should
be examined carefully.
Solid-state power sources are capable of delivering large amounts of energy.
This is by design and the primary mission of the power source. Make sure that
the loads attached match the output voltage and frequency of the Power Source.
First time operation requires a more in depth inspection than would otherwise be
indicated. Specific items to check on first time turn on are:
1.
Proper input voltage brought into the Power Source.
2.
Input connections properly tightened. No nicked or damaged wires,
etc.
3.
Output connections made properly. Also, are loads attached of the
proper voltage and frequency rating.
The operator should refer to Section 3.0, Installation, if there is any doubt
regarding the above conditions.
4.2

INSTALLATION RECORD

During first time operation, the Power Source Installation Record, Table 4.2,
should be completed. This information will record initial operating parameters as
well as providing the beginning of the maintenance and service record.
After installation of the power source, if commissioning service has been
contracted, contact the Pacific Power Source factory for check-out and initial
turn-on. Two weeks should be allowed in scheduling personnel, with a maximum
of two days normally required on site. The first half of the Installation Record
should be completed prior to the arrival of factory personnel. The second half will
be recorded by factory personnel during the commissioning field service.
If a factory visit has not been contracted, the following record should be
completed by properly trained personnel only.
Pacific Power Source ©2013
4-1
OPERATION
Document # 126050-10 Rev E

Advertisement

Table of Contents
loading

Table of Contents