Table 9-1: Inspection Items (Sheet 1 of 2)
1)
Items
1
Alignment mark
2
External lead
3
Working area and manipulator
4
Motors for L- and U-axes
5
Baseplate mounting bolts
6
Cover mounting screws
7
S-,L-,U-axes motor connectors
8
Connector base
9
Balancer
10 Wire harness in manipulator
(Wires for S-, L-, and U-axes)
(Wires for R-, B-, and T-axes)
11 Battery pack in manipulator
12 S-axis speed reducer,
S-axis gear
13 L-axis speed reducer
14 U-axis speed reducer
Schedule
Method
Operation
•
Visual
Check alignment mark accordance and damage at the home position.
•
Visual
Check for damage and deterioration of leads.
•
Visual
Clean the work area if dust or spatter is present.
Check for damage and outside cracks.
•
Visual
Check for grease leakage.
•
Spanner
Tighten loose bolts. Replace if necessary.
Wrench
•
Screwdriver,
Tighten loose bolts. Replace if necessary.
Wrench
•
Manual
Check for loose connectors and tighten if necessary.
•
Manual
Check for loose connectors.
•
Grease Gun
Supply grease. See section 9.3.6.
•
Check for conduction between the main connector of base and
intermediate connector with manually shaking the wires. Check for
wear of protective spring.
•
Replace
•
Replace the battery pack when the battery alarm occurs or the
manipulator drove for 36000 H. See section 9.2.1.
• •
Grease Gun
Check for malfunction. (Replace if necessary.)
Supply grease
Replace grease
• •
Grease Gun
Check for malfunction. (Replace if necessary.)
Supply grease
Replace grease
• •
Grease Gun
Check for malfunction. (Replace if necessary.)
Supply grease
Replace grease
2)
3)
4)
5)
(6000 H cycle). See section 9.3.2.
5)
. (12000 H cycle) See section 9.3.2.
5)
(6000 H cycle). See section 9.3.3.
5)
(12000 H cycle). See section 9.3.3.
5)
(6000 H cycle). See section 9.3.4.
5)
(12000 H cycle). See section 9.3.4.
Inspection
Charge
•
• •
•
• •
•
• •
•
• •
•
• •
•
• •
•
• •
•
• •
• •
• •
•
• •
• •
• •
• •
57 of 100