Figure 13. Removing the cable-management-support arm
Replacing the cable-management arm
Replace the cable-management arm after you install the 2145-CG8 or 2145-CF8 node into the rack.
Replacing the 2145-CG8 and 2145-CF8 cable-management arm
|
The SAN Volume Controller 2145-CG8 or 2145-CF8 use a cable-management arm to route and secure
power cables and other cables.
Replace the cable-management arm after you replace the node in the rack.
To attach the cable-management arm, perform the following steps:
1. At the rear of the rack, install the cable-management-support arm.
Insert both ends of the cable management support arm into the slide rail, as shown by Figure 14 on
page 31.