Verifying The Ieee C37.118/1344 Udp Communication - ABB RET670 Commissioning Manual

Relion 670 series, transformer protection
Hide thumbs Also See for RET670:
Table of Contents

Advertisement

1MRK 504 165-UEN A
Establishing connection and verifying the IEEE C37.118/1344 communication
IEC140000144 V1 EN-US
Figure 16:
Captured synchrophasor data
9.5.2
Transformer protection RET670 2.2 IEC
Commissioning manual

Verifying the IEEE C37.118/1344 UDP communication

After setting both PMU configuration and the UDP client configuration (As
explained in sections
Setting the PMU station communication (PMU
Setting the PMU station communication (PMU configuration)
TCP/UDP client
communication) and making sure that the Ethernet
communication is set up, click Connect on the PMU Connection Tester tool.
IEC140000145 V1 EN-US
Figure 17:
Verifying the UDP communication using PMU Connection Tester
Now it should be possible to see the streaming synchrophasor data.
Verify the communication by following the same steps as in section
the IEEE C37.118/1344 TCP
communication.
Section 9
GUID-F0D1117D-3D0F-498F-A00C-242763F8A4E6 v1
Report),
and
Setting the
IEC140000145-1-en.vsd
Verifying
85