Section 10
Testing IED operation
10.7
94
If the IEC/UCA 61850-9-2LE communication is interrupted during
current injection, the report tool in PCM600 will display the current
that was injected before the interruption.
IEC10000032 V1 EN-US
Figure 20:
PCM600 report tool display after communication interruption
Testing the protection functionality
Each protection function must be tested individually by secondary injection.
•
Verify operating levels (trip) and timers.
•
Verify alarm and blocking signals.
•
Use the disturbance handling tool in PCM600 to evaluate that the protection
function has received the correct data and responded correctly (signaling and
timing).
•
Use the event viewer tool in PCM600 to check that only expected events have
occurred.
1MRK 504 165-UEN A
IEC10000032-1-en.vsd
GUID-125B6F28-D3E5-4535-9CD6-6C056B79F496 v2
Transformer protection RET670 2.2 IEC
Commissioning manual