ABB RET670 Commissioning Manual page 90

Relion 670 series, transformer protection
Hide thumbs Also See for RET670:
Table of Contents

Advertisement

Section 9
Establishing connection and verifying the IEEE C37.118/1344 communication
84
IEC140000143 V1 EN-US
Figure 15:
Stop capturing the IEEE C37.118 synchrophasor data
Open the capture file and observe the captured synchrophasor data. In order to
get the Phasor names on top of each column (See figure 16), the capture
process should start before connecting the PMU Connection Tester to the
PMU, i.e. first start the capturing and then click Connect.
1MRK 504 165-UEN A
IEC140000143-1-en.vsd
Transformer protection RET670 2.2 IEC
Commissioning manual

Advertisement

Table of Contents
loading

Table of Contents