10.1
10.1.1
Transformer protection RET670 2.2 IEC
Commissioning manual
Testing IED operation

Preparing for test

Requirements

IED test requirements:
Calculated settings
Application configuration diagram
Signal matrix (SMT) configuration
Terminal connection diagram
Technical manual
Three-phase test equipment
Process bus, IEC/UCA 61850-9-2LE, MU test simulator, if IEC/UCA
61850-9-2LE process bus communication is used.
PCM600
The setting and configuration of the IED must be completed before the testing can
start.
The terminal diagram, available in the technical reference manual, is a general
diagram of the IED.
Note that the same diagram is not always applicable to each
specific delivery (especially for the configuration of all the binary
inputs and outputs).
Therefore, before testing, check that the available terminal diagram corresponds to
the IED.
The technical manual contains application and functionality summaries, function
blocks, logic diagrams, input and output signals, setting parameters and technical
data sorted per function.
The test equipment should be able to provide a three-phase supply of voltages and
currents. The magnitude of voltage and current as well as the phase angle between
voltage and current must be variable. The voltages and currents from the test
equipment must be obtained from the same source and they must have minimal
harmonic content. If the test equipment cannot indicate the phase angle, a separate
phase-angle measuring instrument is necessary.