Prepare pH and DO sensors

Instructions
Follow the instructions below to connect the sensor adapters to the pH and DO bag
sensor ports.
Step
1
2
ReadyToProcess WAVE 25 Operating Instructions 29009597 AD
NOTICE
Be careful to connect the sensors to the correct ports on
ReadyToProcess CBCU. Identification stickers are provided to label
the connectors.
NOTICE
In dual mode, be careful to connect the sensors for the left and
right Cellbag bioreactors to the correct ReadyToProcess CBCU. This
is easier if the respective ReadyToProcess CBCU units are placed
on the left and right sides of the rocker respectively.
Action
Remove the Cellbag bioreactor from its protective cover bag.
NOTICE
Exposure to intense light will cause deterioration of
the optical sensors on the Cellbag bioreactor. To avoid
unnecessary light exposure, remove the protective
cover bag just prior to use.
Place the Cellbag bioreactor on a steady surface with the bag sensor ports
facing upwards.
The optical sensor spots have different colors. The spot on the pH sensor
bag port is white/yellow and the spot on the DO sensor port is pink/black. If
both pH and DO sensors are used, a separate fiber cable is needed for each
sensor.