5.3.8.5

Commissioning the SmartWire-DT network

Switching on for initial startup, a replacement or a changed SmartWire-DT configuration
Requirement:
All SmartWire-DT modules must be connected to each other via SmartWire-DT cables.
The SmartWire-DT network must be connected to the SmartWire-DT interface.
The power supply for the device and for SmartWire-DT must be on and connected.
The SmartWire-DT master's POW LED must be lit up with a solid light.
The SmartWire-DT status LEDs of the connected SmartWire-DT modules must be flashing or
showing a solid light.
A PLC project with configured SWD-Master exists (project configuration).
The PLC runtime system must be installed on the device.
Procedure:
1
Press the configuration button «Config» for at least two seconds.
The SWD LED of the SmartWire-DT Master interface begins to flash orange and the Smart-
Wire-DT status LEDs on the connected SmartWire-DT slaves flash.
The SmartWire-DT master interface's SWD LED will start flashing with a green light
All SmartWire-DT modules are addressed.
The SmartWire-DT network's physical configuration will be stored in the device's non-volatile
memory as a target configuration.
The SmartWire-DT master interface's SWD LED will start showing a solid green light.
2
Download the PLC project (XSoft-CoDeSys-2) onto the device.
If the project configuration is identical to the stored target configuration, the Config LED lights
up green and the data exchange of the input and output data can start.