2-2 Installation

Installation and wiring for the N15K0, H18K5 and smaller drives,
and wiring for the N18K5 and X22K0 and larger drives are
carried out with the front cover removed.
Before removing the front cover, always remove the operation
panel from the unit. If the front cover is removed without
removing the operation panel, the unit could drop off the
operation panel and be damaged. To remove the operation
panel, press in the left and right latches inward and pull off the
panel as shown on the right.
When the installation and wiring work are completed, install the
front cover, and then install the operation panel. At that time,
make sure that the latches on the left and right of the operation
panel are securely caught.
(1) N15K0, X18K5 and smaller (Fig. 2.2)
Fix the VAT2000 on the four corners, note that
the lower two mounting holes are notched.
Remove the front cover, and wire to the main
circuit and control terminal block.
2. Installation and Wiring
Fig 2.2
(2) N18K5, X22K0 and larger (Fig. 2.3)
Fix the VAT2000 on the four corners, note that
the lower two mounting holes are notched.
These frames weitg more than 25kg, so
installation by two workers is recommended.
Fig 2.3