Primary Boom

How to Shim the Boom
1 Measure each wear pad.
Result: Each wear pad meets minimum
specification. Proceed to step 2.
Result: Each wear pad does not meet minimum
specification. Replace any wear pad that does
not meet minimum specification. Proceed to
step 2.
2 Extend the boom until the wear pads are
accessible.
3 Loosen the wear pad mounting fasteners.
4 Install the new shims under the wear pad to
obtain zero clearance and zero drag.
5 Tighten the mounting fasteners.
6 Extend and retract the boom through an entire
cycle. Check for tight spots that could cause
binding or scraping.
Note: Always maintain squareness between the
outer and inner boom tubes.
Part No. 88619
Wear Pad Specifications
Primary boom wear
pad specifications
Top, bottom and
side wear pads
(platform end of boom)
Side and bottom wear pads
(pivot end of boom)
Top wear pads
(pivot end of boom)
Secondary boom wear
pad specifications
Top, and side wear pads
(extension end of boom)
Bottom wear pads
(extension end of boom)
Top wear pads
(pivot end of boom)
Bottom and side wear pads
(pivot end of boom)
Z-80/60
Section 4 • Repair Procedures
BOOM COMPONENTS
Minimum
15.9 mm
12.7 mm
15.9 mm
Minimum
15.9 mm
12.7 mm
12.7 mm
22.2 mm
5
/
inch
8
1
/
inch
2
5
/
inch
8
5
/
inch
8
1
/
inch
2
1
/
inch
2
7
/
inch
8
4 - 33

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents