June 2011
REV D
E-6
Perform Engine Maintenance -
Deutz 2011 Models
Engine specifications require that this procedure
be performed every 5000 hours.
Proper engine maintenance, following the engine
manufacturer's maintenance schedule, is essential
to good engine performance and service life.
Failure to perform the maintenance procedures
can lead to poor engine performance and
component damage.
Required maintenance procedures and additional
engine information are available in the
Deutz BF4L2011 Operation Manual
(Deutz part number 0297 9929) OR the
Deutz TD2011 Operation Manual
(Deutz part number 0312 3547).
Deutz BF4L2011 Operation Manual
Genie part number
Deutz TD2011 Operation Manual
Genie part number
Part No. 88619
Section 3 • Scheduled Maintenance Procedures
To access the engine:
1 Remove the engine tray retaining fastener
located under the engine tray. Swing the engine
tray out and away from the machine.
2 Install the fastener that was just removed
through the engine tray and into the engine tray
anchor hole in the turntable.
84794
139320
Z-80/60
CHECKLIST E PROCEDURES
Crushing hazard. Failure to install
the fastener into the engine tray
anchor hole to secure the engine
tray from moving could result in
death or serious injury.
3 - 67