Dismantling and cleaning the burner and
the exchanger
- Remove the front and top panel of the boiler
(see the operations described on page 66).
- Remove the wiring (5) from the fan (6)
- Unscrew the two screws (8) that fasten the
fan (6) to the air conveyor (9)
- Unscrew the four screws (10) that fasten the
fan assembly (6) to the exchanger, using a 10
mm socket wrench
- Remove the gasket (11) and remove the
burner (12)
- Remove the electrode plate (13), check the
condition of the electrode and replace if
necessary.
Once the cleaning operations have been
completed, reassemble the components in
the reverse order.
b
Check that the gas connection is tight.
68
FRANÇAIS
Démontage et nettoyage du brûleur et de
l'échangeur
- Enlever les panneaux avant et supérieur de
la chaudière (voir les passages décrits p. 65).
- Débrancher le câblage (5) du ventilateur (6).
- Dévisser les deux vis (8) qui fixent le ventila-
teur (6) au convoyeur de l'air (9).
- Avec une clé à tube de 10 mm, dévisser les
quatre vis (10) qui fixent le groupe ventilateur
(6) à l'échangeur.
- Enlever le joint (11) et sortir le brûleur (12)
- Démonter la platine porte-électrode (13),
vérifier l'état de l'électrode et, le cas échéant,
la remplacer.
Une fois les opérations de nettoyage ter-
minées, remonter les composants en
procédant à l'inverse de ce qui a été décrit.
b
Vérifier que le raccordement gaz est
étanche.