Connecting Commercial Power; How To Use This Chapter; Chapter Task List - Nortel SONET AccessNode 800A Series Manual

Outside plant cabinet installation
Table of Contents

Advertisement

Connecting commercial power

This chapter provides information for connecting commercial power to the ac
load box option and to the power pedestal option for the Series 800A cabinet.
The Series 800A cabinet is equipped with one of two optional ac input panels:
the ac load box or the ac power pedestal. Use these procedures to connect the
cabinet to the local commercial ac source.

How to use this chapter

In the following table, you will find a list of the procedures to connect the
commercial power to the AccessNode S800A Outside Plant (OSP) cabinet.
Perform the procedures in the order listed. If you cannot successfully complete
these procedures, contact your next level of support.

Chapter task list

Task
Connecting earth ground to the ac load box
Wiring the ac load box as a branch circuit
Wiring the ac load box as a main service
entrance
Connecting earth ground to the ac power
pedestal
Wiring the ac power pedestal
AccessNode Series 800A Outside Plant Cabinet Installation 323-3001-210 Issue 1.0
See
Procedure 3-1 on page 3-5
Procedure 3-2 on page 3-7
Procedure 3-3 on page 3-10
Procedure 3-4 on page 3-13
Procedure 3-5 on page 3-17
3-1
3-

Advertisement

Table of Contents
loading

Table of Contents