Routing and terminating OSP T1 and
maintenance pairs
This chapter describes in detail the installation procedures for:

How to use this chapter

In the following table, you will find a list of the procedures to route and
terminate the outside plant T1 and maintenance cable pairs for the AccessNode
S800A Outside Plant (OSP) cabinet. Perform the procedures in the order
listed. If you cannot successfully complete these procedures, contact your next
level of support.

Chapter task list

Task
Routing and terminating OSP T1 and
maintenance pairs

Prerequisites for installation

The choice of site and compliance with local regulations (such as the
applicable electrical codes, right-of-way easements, and noise requirements)
are the responsibility of the operating company.
The prerequisites for routing and terminating the T1 and maintenance cabling
include:
AccessNode Series 800A Outside Plant Cabinet Installation 323-3001-210 Issue 1.0
routing the T1 and maintenance pair cables in the S800A cabinet
terminating the T1 and maintenance pair cabling
The cabinet has been installed on the selected concrete pad as defined in
Chapters 1, 2, 3 and 4 of this practice.
All the required drawings, local installation instructions, job
specifications, and other documentation are available and ready for use.
All hardware and materials are available and have been checked for
completeness and readiness for the installation.
— outside plant cable hole and conduit plugging compound
See
Procedure 5-1 on page 5-3
5-1