Cable Entry - Nortel SONET AccessNode 800A Series Manual

Outside plant cabinet installation
Table of Contents

Advertisement

Cable entry

The S800A cabinet is constructed with cable conduit entry ports located in the
bottom of the end compartments of the cabinet (see Figure 4-1 on page 4-7).
In the termination compartment there are four 4.50-inch inside diameter (ID)
openings for 4.00-inch trade size conduit and on, 2.00-inch ID opening for
1.50-inch trade size conduit.
Table 4-1 shows the conduit openings in the termination compartment.
Table 4-1
Termination compartment conduit openings
Opening size
4.50 inches
(11.43 cm)
4.50 inches
(11.43 cm)
4.50 inches
(11.43 cm)
4.50 inches
(11.43 cm)
2.00 inches
(5.08 cm)
AccessNode Series 800A Outside Plant Cabinet Installation 323-3001-210 Issue 1.0
Note: All trade sizes listed are based on Schedule 40 permanent virtual
circuit (PVC).
Conduit trade size
4.00 inches
(10.16 cm)
4.00 inches
(10.16 cm)
4.00 inches
(10.16 cm)
4.00 inches
(10.16 cm)
1.50 inches
(3.81 cm)
Installing the OSP cables 4-3
Function
VF - pairs 1–600 cable entrance
VF - pairs 601–1200 cable entrance
VF - miscellaneous cable entrance
VF - HF or fiber cable entrance
Earth ground rod connection entrance