7-30 Routing and splicing the fiber cable
Procedure 7-3 (continued)
Routing the OSP fibers in split flex tubing to the FPP
Step
22
23
24
Figure 7-17
Routing the patch cords into the FPP (right rear view)
Tie-wrap
AccessNode 323-3001-210 Issue 1.0
Action
Measure the length of the tubing to establish the point at which the tubing is
to be butted.
Note: The tubing should extend 1/2-inch (1.27 cm) further than the cable tie
strap located inside the interior left rear of the FPP.
Butt the tubing.
Note: Ensure that you do not cut the patch cords inside the tubing.
Route the patch cords and the tubing into the access hole in the FPP located
on the rear right side as shown in Figure 7-17.
Note: Maintain at least the minimum bend radius (3.0 inches/76 mm) for the
fiber pigtails or patch cords installed.
Ground lug
Patch cords in
spiral wrap tubing
—continued—
FW-15141
FW-15141
Bonding clamp
Ground wire
Swing frame