1-8 Installing the pad

Procedure 1-1

Preparing the poured-in-place cabinet mounting pad

The anchor plate assembly kit is required for construction of the pad conduit.
Refer to Engineering and Ordering, 323-3001-032, in the Engineering,
Configuration and Ordering Guide, Volume 1, for ordering information.
This procedure applies to the following types of pad arrangements:
Prerequisites for installation
The operating company is responsible for the choice of site and compliance
with local regulations such as the applicable electrical codes, right-of-way
easements, and noise requirements.
Installation procedures assume the following:
Tools required
A spirit level tool is required.
Materials (concrete forms as required)
AccessNode 323-3001-210 Issue 1.0
standard raised
adjacent attached pedestal
remote pedestal
standard wide pad
The cabinet concrete pad is to be installed above local flooding levels.
A minimum clearance of 32 inches (81 cm) is required on all sides of the
cabinet for door clearance.
All hardware and materials are available, and have been checked for
completeness and readiness for the installation.
All the required drawings, local installation instructions, job
specifications, and other documentation are available and ready for use.
2x8s (cut exactly 6 inches wide)
2x6s (cut exactly 4 inches wide)
double-headed nails (to make form removal easier)
miscellaneous braces and stakes (1x2s and 2x2s as required)
10 gauge x 6-inch spacing of welded wire mesh (for concrete
reinforcement)
reinforcing rods (#4x10-inch spacing) when required