Ring setup and testing: integration procedures

Manual switching tests

............................................................................................................................................................................................................................................................
Description
This test will initiate switching commands from the CIT and verify proper switching and
LED indications.
Important!
switching.
Manual switching test procedure
........................................................................................................................................................................................................................
Enter an STS-1 add/drop cross-connection between an equipped Function Unit and the
1
Main OLIU. Select Configuration -> Cross-Connections... and use the Cross-Connection
Wizard to enter an add/drop cross-connection.
........................................................................................................................................................................................................................
Select Fault -> Protection Switch...
2
........................................................................................................................................................................................................................
Under Path Protection choose Path m-1-1 and click Select.
3
........................................................................................................................................................................................................................
Note the Active Path (m1 or m2).
4
........................................................................................................................................................................................................................
Choose Switch Type: Manual.
5
........................................................................................................................................................................................................................
Click Apply.
6
........................................................................................................................................................................................................................
Verify that the Active Path: has changed (m1 to m2 or m2 to m1).
7
........................................................................................................................................................................................................................
8
Repeat
............................................................................................................................................................................................................................................................
6 - 1 4
An STS-1 cross-connect is required in order to perform manual
Step 2
through
Step 7
to verify a switch back to the original ring.
Manual switching tests