UPS System Installation
1.
If not already accomplished, use a forklift or pallet jack to move the cabinet to the installation area, or as
close as possible, before unloading from the pallet. If possible, move the cabinet using the pallet. Insert
the forklift or pallet jack forks from the right side of the pallet (facing the cabinet), between the supports on
the bottom of the pallet (see
must be moved using the cabinet front or rear fork lift slots, see the caution statement at the beginning of
this procedure.
2.
Remove the three bolts securing the left side shipping bracket to the cabinet and three bolts securing the
bracket to the pallet (see
permanently, retain the shipping bracket and securing hardware for later use.
3.
Remove the three bolts securing the right side shipping bracket to the cabinet and three bolts securing the
bracket to the pallet (see
permanently, retain the shipping bracket and securing hardware for later use.
4.
Using a forklift (see the caution statement at the beginning of this procedure), raise the UPS cabinet
section until the cabinet bottom clears the pallet by approximately 3 mm (1/8").
5.
Pull the pallet from under the UPS cabinet. Discard or recycle the pallet in a responsible manner.
6.
Using a forklift (see the caution statement at the beginning of this procedure), move the UPS cabinet to
the final installed location.
7.
Carefully lower the UPS cabinet until the cabinet base contacts the floor.
8.
If permanently mounting the system, proceed to Step 9; otherwise, continue to Step 11.
NOTE
9.
Using the retained hardware, reinstall the shipping brackets removed in Steps 2 and 3 to the left and right
side of the UPS cabinet with the angle facing outward (see
10. Secure the cabinet to the floor with customer-supplied hardware.
11. If installing a FI-UPM, proceed to
12. If installing a battery system, proceed to
13. If installing a tie cabinet or distribution panel for a distributed bypass system, proceed to
4.5 Distributed Bypass Tie Cabinet
4.6 Installing UPS External and Battery Power
42
Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201716—Rev 14
Figure 8
for the UPS cabinet center of gravity measurements). If the cabinet
Figure
11). Remove the left side shipping bracket. If installing the cabinet
Figure
12). Remove the right side shipping bracket. If installing the cabinet
DO NOT reinstall the left side shipping bracket, if installing a Field Installed UPM (FI-
UPM).
4.3 Field Installed UPM
4.4 Battery System
Installation; otherwise, proceed to
Figure 11
and
Installation; otherwise, proceed to Step 12.
Installation; otherwise, proceed to Step 13.
Wiring.
Figure
12.

Advertisement

Table of Contents
loading

Table of Contents