Table 7. Input/Output Ratings and External Wiring Requirements for the Power Xpert 9395-550/275 – 480V, Separate
Battery (Continued)
Basic Unit Rating
Input and Output Voltage
AC Output to Critical Load (Five Wire)
Full Load Current
(3) Phases, (1) Neutral, (1) Ground
Minimum Conductor Size
Number per Pole
NOTE: Callout letters A, B, C, and D map to
NOTE: Because of the future upgradability to a fully rated 550 kVA UPS with the addition of the FI-UPM, the UPS wiring is specified
for 550 kVA.
NOTE If a 4-pole Automatic Transfer Switch (ATS) is used to connect the UPS to a generator or alternative input source, it may
interrupt the UPS input neutral during its transition between sources. For the 9395 UPS:
The ATS transition must be open in both directions. The "break" time for the contacts must be at least 50 ms. This allows the UPS to
operate properly, however it is important to evaluate whether the critical load will function properly as its neutral reference is rapidly
(50 ms) switched. Note also that if the UPS load is on bypass, an ATS switchover with interruption of the neutral, will interrupt the
return current path and cause a loss of all phase-to-neutral loads.
If an overlapping neutral or make-before-break ATS switch is used, the neutrals must overlap for a minimum of 50 ms during the
transition.
Table 8. Input/Output Ratings and External Wiring Requirements for the Power Xpert 9395-550/275 – 400V, Separate
Battery
Basic Unit Rating
Input and Output Voltage
AC Input to UPS Rectifier (0.98 Minimum pF)
Full load current plus battery recharge current
(3) Phases, (1) Ground
Minimum Conductor Size
Number per Phase
AC Input to UPS Bypass (Four Wire)
Full Load Current
(3) Phases, (1) Ground
Minimum Conductor Size
Number per Phase
AC Input to UPS Bypass (Five Wire)
Full Load Current
(3) Phases, (1) Neutral, (1) Ground
Minimum Conductor Size
Number per Phase
Units
kVA
kW
Volts
Amps
D
AWG or kcmil
(each)
Figure
54. Callout letters B, C, and D map to
Units
kVA
kW
Volts
Amps
A
AWG or kcmil
(each)
Amps
B
AWG or kcmil
(each)
Amps
B
AWG or kcmil
(each)
Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201716—Rev 14
UPS Installation Plan and Unpacking
Rating 50/60 Hz
225
225
450
205
250
410
480/480 480/480 480/480 480/400
271
331
541
300
300
300
(4)
(4)
(4)
Figure
55.
Rating 50/60 Hz
225
225
450
205
250
410
400/400 400/400 400/400 400/400
453
741
370
300
300
300
(4)
(4)
(4)
325
397
650
350
350
350
(3)
(3)
(3)
325
397
650
500
500
500
(3)
(3)
(3)
500
550
455
501
480/480
601
662
300
300
(4)
(4)
500
550
455
500
400/400
823
905
300
300
(4)
(4)
722
794
350
350
(3)
(3)
722
794
500
500
(3)
(3)
29