Siemens SINAMICS G120 Operating Instructions Manual page 120

Low voltage converters, chassis and wall/panel mounted devices with cu230p-2 control units
Hide thumbs Also See for SINAMICS G120:
Table of Contents

Advertisement

Commissioning
5.3 Commissioning using a BOP-2 operator panel
Procedure
Proceed as follows to carry out basic commissioning:
1.
2.
3.
4.
5.
6.
7. Overload capability and supply voltage of the inverter
120
Press the ESC key.
Press one of the arrow keys until the BOP-2 displays the "SETUP" menu.
In the "SETUP" menu, press the OK key to start basic commissioning.
If you wish to restore all of the parameters to the factory setting before
the basic commissioning:
4.1.
Switch over the display using an arrow key: nO → YES
4.2.
Press the OK key.
Whether the inverter displays this commissioning step depends on the
Power Module being used:
• PM230 Power Module:
The inverter skips this step.
• PM240 or PM240-2 Power Modules:
Select one of the two application classes:
– Standard Drive Control
– Dynamic Drive Control
– When selecting application class "EXPERT", follow this
• Power Module PM330:
Select application class "Dynamic Drive Control"or select
"EXPERT"and then follow these instructions.
See also: Basic commissioning with application classes
(Page 127).
Motor standard
KW / 50HZ
HP / 60HZ
KW / 60HZ
7.1.
7.2.
See also: Basic commissioning with application classes
(Page 127).
handling instruction.
IEC
NEMA
IEC 60 Hz
Overload capability
HIGH OVL
Load cycle with "High Overload"
LOW OVL
Load cycle with "Low Overload"
Inverter supply voltage
Operating Instructions, 04/2015, FW V4.7 SP3, A5E34257946B AB
Converter with CU230P-2 Control Units