F 158 VtgOnAC1Det
W 159 VtgOnAC1DetSlv1
W 160 VtgOnAC1DetSlv2
F 162 OvrCurDet
W 163 OvrCurDetSlv1
W 164 OvrCurDetSlv2
F 166 Overload5min
W 167 Overload5minSlv1
W 168 Overload5minSlv2
Operating Manual
Level Cause
2
Voltage at AC connection
Line conductor L1: The master
has measured an undesired volt-
age at connection AC1.
1
Voltage at AC connection
Line conductor L2: slave 1 has
measured an undesired voltage
at connection AC1.
1
Voltage at AC connection
Line conductor L3: slave 2 has
measured an undesired voltage
at connection AC1.
2
Too much current is flowing
through the DC connection of
the master.
1
Too much current is flowing
through the DC connection of
slave 1.
1
Too much current is flowing
through the DC connection of
slave 2.
3
The device at L1 (Master) has
been loaded over its five-minute
rated capacity.
1
The device at L2 (slave 1) has
been loaded over its five-minute
rated capacity.
1
The device at L3 (slave 2) has
been loaded over its five-minute
rated capacity.
10 Troubleshooting
Corrective measures
A bypass switch may have bridged the
internal transfer relay.
• Ensure that the bypass switch is in
the position for operation with the
Sunny Island.
• Ensure that the bypass switch is in
the position for operation with the
Sunny Island.
An external energy source (e.g., genera-
tor) may have been connected to the
connection AC1.
• Disconnect external energy source
from connection AC1 and connect
to connection AC2 (see the
Sunny Island inverter installation
manual).
• Reduce the power of the loads.
• Reduce the power of the loads.