16. FLM LIQUID COOLING CIRCUIT

About this chapter
This chapter describes how to diagnoses and to maintain the liquid cooling circuit of the FLM projector.
W
ARNING
W
ARNING
projector should have sufficiently cooled down (minimum 2 hours).
W
ARNING
vessel), unless stated explicitly in the servicing procedure.
Tools used in the liquid cooling servicing procedures
A
Image 16-1
A
Syringe with plastic tube (60 cm) and male valved fitting.
B
Two plastic tubes of 60 cm with male valved fitting.
C
60 cm plastic tube with female valved fitting.
D
Female valved fitting (to create female/female valved fitting adaptor).
E
Bottle with 1 liter cooling liquid.
F
Empty bottle with a volume of 1 liter.
G Air pump with Shrader type air hose fitting.
Order info liquid cooling
Order number
R395198K
B1909086K
Overview
Safety
Introduction
Diagnostics
Pressure verification of the liquid cooling circuit
Draining the liquid cooling circuit
Filling the liquid cooling circuit
Refreshing the liquid cooling circuit
Expelling air from the liquid cooling circuit
Pressurizing the liquid cooling circuit
Calibrating the liquid cooling circuit
R59770072 FLM SERIES 19/03/2007
:
All procedures in this chapter may only be performed by "qualified service technicians" .
:
All actions performed on the liquid cooling circuit should occur in ambient conditions (25°). The
:
Do not change the air pressure of a calibrated liquid cooling circuit (see marking on pressure
B
C
Description
Complete liquid cooling refill kit. Includes tubes, valved fittings, syringe, air pump, two plastic bottles of 1
liter filled with cooling liquid.
Four bottles of 1 liter filled with cooling liquid. (no additional tools)
D
E
1L
16. FLM liquid cooling circuit
F
G
153

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Flm r20+Flm hd18Flm hd14

Table of Contents