CHAPTER 6

Preparation Overview

Site Preparation Checklist for EX4200 Switches

Table 30: Site Preparation Checklist

Item or Task
Environment
Verify that environmental factors such as
temperature and humidity do not exceed switch
tolerances.
Power
Measure distance between external power
sources and switch installation site.
Locate sites for connection of system
grounding.
Calculate the power consumption and
requirements.
Hardware Configuration
Copyright © 2015, Juniper Networks, Inc.
Site Preparation Checklist for EX4200 Switches on page 61
Environmental Requirements and Specifications for EX Series Switches on page 63
General Site Guidelines on page 66
Site Electrical Wiring Guidelines on page 67
Rack Requirements for EX4200 Switches on page 69
Cabinet Requirements for EX4200 Switches on page 70
Requirements for Mounting an EX4200 Switch on a Desktop or Wall on page 71
Clearance Requirements for Airflow and Hardware Maintenance for EX4200
Switches on page 72
The checklist in
Table 30 on page 61
preparing a site for EX4200 switch installation.
For More Information
"Environmental Requirements and
Specifications for EX Series Switches"
on page 63
"Power Specifications for EX4200
Switches" on page 75
summarizes the tasks you need to perform when
Performed by
Date
61