Installation
RP9 Radio-Pad
Before connecting the Radio-Pad, isolate ALL power from the
control panel (AC mains and battery), do not continue if there
is still power present on the control panel.
To install the Radio-Pad onto the control panel:
•
Connect the Molex connector of the RPD-Com lead to
Com2 on the control panel
•
Connect the 25-Way D-Type connector of the RPD-Com
to the Radio-Pad
•
Locate the power lead connector into the socket at the
bottom of the Radio-Pad
•
Connect the Black lead to the DC- terminal on the control
panel
•
Connect the lead with the White stripe to the DC+
terminal on the control panel
•
Follow the procedure for Registering the Radio-Pad
Registering the Radio-Pad
Whenever a Paknet Radio-Pad is installed or moved, it must
be registered onto the network. To do this:
•
Press and hold the test button on the front of the Paknet
Radio-Pad
•
With the test button still pressed, connect power to the
control panel and wait for the yellow service light on the
Radio-Pad to flash
•
Release the test button
Within 2 minutes the yellow service light should stop flashing
and remain steady. This means that the Paknet Radio-Pad
has now selected and locked on to the Base Station with the
strongest signal.
The Paknet Radio-Pad should be re-registered on every site
visit, this is to ensure that any new Vodafone Packet Radio
Service Base Stations in the vicinity are recorded by the
Paknet Radio-Pad.
Programming the Radio-Pad
•
Program Com 2 for Radio-Pad operation (see page 76
for details)
•
Refer to the Radio-Pad installation guide for full
programming details.
24
Premier 48, 88, 168 & 640 Installation Manual
GSM Module
Before connecting the GSM Module, isolate ALL power from
the control panel (AC mains and battery), do not continue if
there is still power present on the control panel.
To install the GSM Module onto the control panel:
•
Connect the Molex connector of the GSM-Com lead to
Com2 on the control panel
•
Connect the RJ45 connector of the GSM-Com to the
GSM Module
•
Locate the power Jack Plug into the socket at the bottom
of the GSM Module
•
Insert a SIM card into the bottom of the GSM Module
•
Connect power to the control panel
Programming the GSM Module
•
Program Com 2 for GSM Module operation (see page 76
for details)
•
Refer to the GSM Module installation guide for full
programming details.
AV Module
Before connecting the AV Module, isolate ALL power from the
control panel (AC mains and battery), do not continue if there
is still power present on the control panel.
To install the AV Module onto the control panel:
•
Connect one end of the patch lead on to the Expansion
Port of the AV Module
•
Connect one other end of the patch lead on to the
Expansion Port of the control panel
Programming the AV Module
•
Program the Expansion Port for AV Module operation
(see page 76 for details)
•
Refer to the AV Module installation guide for full
programming details.
ComIP Module
Before connecting the ComIP Module, isolate ALL power from
the control panel (AC mains and battery), do not continue if
there is still power present on the control panel.
To install the ComIP onto the control panel:
•
Connect one end of the patch lead on to JP1 of the
ComIP
•
Connect one other end of the patch lead on to Com1 or
2 of the control panel
Programming the ComIP Module
•
Program Com1 or 2 for ComIP Module operation (see
page 76 for details)
•
Refer to the ComIP Module installation guide for full
programming details.