9. Place the four bolts for the caged nuts within reach.
10. Slide the switch into the rails.
11. Put the switch into place and screw the bolts into the nuts from step 6. If the power cable is on
this side of the switch, feed the power cable into the slot in the bracket before screwing it to the
vertical support.Tighten the bolts to 9.2 Nm or 81.5 pound inches.
12. Tighten all of the screws to 9.2 Nm or 81.5 pound inches.
13. Ground the switch
14. Plug in the power cables.
15. Check the Status LEDs and confirm that all of the LEDs show status lights consistent with
normal operation.
diately.
It can take up to 5 minutes to boot up, during which time the status LED may indicate
red.
16. You can start connecting all of the cables to the switch.
18
Mellanox Technologies

Figure 10: Connect Bracket to Rack Vertical support

Warning: Any yellow status LEDs is cause for concern and must be dealt with imme-