Ups Setup; Up Setup; Inspecting The Equipment - Eaton Powerware 9355 Parallel User Manual

Parallel ups 10/15 kva
Table of Contents

Advertisement

Chapter 3

Inspecting the Equipment

®
EATON Powerware
9355 Parallel UPS (10/15 kVA) User's Guide

UPS Setup

This chapter describes:
S
Equipment inspection
S
Floor loading and clearances
S
Unloading the cabinet(s)
The instructions are intended for the chief operator/system supervisor,
electrical consultants, and installation electricians. Local regulations and
electrical code must be followed during the UPS installation.
If any equipment has been damaged during shipment, keep the shipping
and packing materials for the carrier or place of purchase and file a claim
for shipping damage. If you discover damage after acceptance, file a
claim for concealed damage.
To file a claim for shipping damage or concealed damage: 1) File with
the carrier within 15 days of receipt of the equipment; 2) Send a copy of
the damage claim within 15 days to your service representative.
NOTE Check the battery recharge date on the packaging label. If the date has expired and
the batteries were never recharged, do not use the UPS. Contact your service representative.
S
164201601 Rev A www.powerware.com
7