Power Connection Cable Routing And Conduit Placement 15/25/30 Kva; Figure 6-3 15030Kva Cable Routing - Toshiba 4200FA Installation And Operation Manual

Three-phase 15/25/30/50 kva ups
Hide thumbs Also See for 4200FA:
Table of Contents

Advertisement

6.1.4

Power Connection Cable Routing and Conduit Placement 15/25/30 kVA

The following illustrates the proper cable routing that should be followed during the power
connection process of the 15/25/30 kVA.
Note:
1) Input and Output conductors
shall be installed in separate
conduits, and installed in
accordance with the latest
edition of NEC and the Local
Authority having jurisdiction.
2) Battery conductors shall be
installed in a separate conduit
and be of low resistance type.
24
CONDUIT
MOUNTING
PANEL

Figure 6-3 15030kVA Cable Routing

INPUT
OUTPUT
BATTERY
CONDUIT
CONDUIT
CONDUIT
4200FA Installation and Operation Manual

Advertisement

Table of Contents
loading

Table of Contents