Chapter 2
Installing the Cisco MDS 9216 Switch
Send documentation comments to mdsfeedback-doc@cisco.com.
Note

Verifying Installation of a Switching or Services Module in Slot 2

Step 1
Step 2
Step 3
Step 4
Note

Removing and Installing Power Supplies

78-16165-01
d.
While pressing down, simultaneously close the left and right ejector levers to
fully seat the module in the backplane connector. The ejector levers are fully
closed when they are flush with the module faceplate.
Ensure the ejector levers are fully closed before tightening the captive screws.
Failure to fully seat the module in the backplane connector can result in error
messages.
Tighten the two captive screws on the module.
e.
To verify the module installation in slot 2, follow these steps:
Verify that the ejector levers of the module are fully closed (parallel to the
faceplate) to ensure that the module is fully seated in the backplane connectors.
Check the captive screws of the module, the power supply, and the fan module,
and tighten any loose captive screws.
If the slot is to remain empty, verify that a filler panel is installed and that the
screws holding the panel in place are tightened.
Turn on the power supply switches to power up the system and check the LEDs
on the module.
For information about how to check connectivity of the module, refer to the
Cisco MDS 9000 Family Configuration Guide.
The Cisco MDS 9216 Switch supports dual 845 Watt AC power supplies that
monitor output voltage and provide status to the supervisor module.
Removing and Installing Components
Cisco MDS 9216 Switch Hardware Installation Guide
2-27