Connect the rudder trim to the arm of the torque tube and secure with bolt, washer, nut and cotter
pin. A thin washer is installed under the nut which is tightened only finger tight.
j.
Connect the ends of the rudder control cables (19) to the arms provided on the torque tube and
secure with bolts, washers, nuts and cotter pins (20). Allow the cable ends to rotate freely.
k. Swing the tee bar into place and secure with attachment bolts, washers and nuts (15) with the bolts
inserted in through each side of the floor tunnel.
l.
Connect the stabilator control cables to the lower end of the tee bar with bolt, washer and nut, and
secure with cotter pin. (Refer to Figure 5-6.) Allow cable ends to rotate freely.
m. Set rudder cable tension per specifications in Table V-II. Check rigging and adjustment per
Paragraph 5-36.
n. Check safety of bolt and turnbuckles.
o. Install the floor tunnel plate and secure with screws. Fasten the tunnel carpet in place.
p. Install the rudder trim cover and control knob.
q. Install the access panel to the aft section of the fuselage.
5-29.
RUDDER CONTROLS.
5-30.
REMOVAL OF RUDDER CONTROL CABLES. (Refer to Figure 5-16.)
a. Remove the access panel to the aft section of the fuselage.
b. Disconnect the cable(s) to be removed at the turnbuckle (12 or 13) in the aft section of the fuse-
lage.
c. Remove either forward rudder cable (10 or 11) by the following procedure:
1. Remove the rear seat or floor panel, whichever applies, and the front seats.
2. Remove the cable guard pin (7) from the underside of the pulley cluster (9) that is located in
the aft area of the flap torque tube.
3. From within the area aft of the main spar, remove the cable rub blocks (6) that are attached to
the spar housing by removing the block attaching screws.
4. Remove the rudder trim knob and the cover attaching screws.
5. Remove the tunnel plate just aft of the tee bar by removing enough carpet from the tunnel to
allow the plate attaching screws and the plate to be removed.
6. Move the cable guard pin (4) located under the pulley cluster (5) just aft of the tee bar by
removing the cotter pin from the exposed end and sliding it to the left or right, as required.
7. Disconnect the end of the cable from the arm on the rudder pedal torque tube by removing the
cotter pin, nut, washer and bolt (2).
8. Draw the cable from the floor tunnel.
d. Remove aft rudder control cables (14 or 15) by the following procedure:
1. Remove the tail cone fairing by removing its attaching screws.
2. Disconnect the cable (14 or 15) from the rudder horn (17) by removing cotter pin, nut, washer
and bolt (16).
3. Draw the cable through the fuselage.
5-31.
INSTALLATION OF RUDDER CONTROL CABLES. (Refer to Figure 5-16.)
a. Install either forward rudder control cable (10 or 11) by the following procedure:
1. Draw the control cable through the floor tunnel.
2. Connect the end of the cable to the arm on the rudder pedal torque tube by installing bolt,
washer, nut and cotter pin (2). Allow the cable end free to rotate on the arm.
3. Connect the cable to the aft control cable at the turnbuckle (12 or 13) in the aft section of the
fuselage. If the aft control cables are not installed, install at this time per step b. Ascertain that each cable is in
the groove of its pulley.
Revised: February 28, 1995
1H15
Island Enterprises
SURFACE CONTROLS

Advertisement

Table of Contents
loading

This manual is also suitable for:

Warrior ii pa-28-161 1995Warrior iii pa-28-161 1995

Table of Contents