Innova 2100-IQ, 3100/3100-IQ, 4100/4100-IQ Cardiovascular Imaging System Pre-Installation Manual
GE Healthcare
Chapter 2 Innova Systems
DO NOT CONNECT THE UPS BATTERIES PRIOR THE COMMISSIONING OF
THE UPS (INITIAL POWER UP).
General safety instructions
•
Move the UPS in an upright position in its original package to the final
destination room.
To lift the cabinets, use a forklift or lifting belts with spreader bars.
•
Check for sufficient floor and elevator loading capacity.
•
Check the integrity of the UPS equipment carefully.
•
If you notice visible damage, do not install or start the UPS. Contact the nearest
Service Center immediately.
WARNING! RISK OF ELECTRICAL SHOCK: Do not remove covers; there are
no user serviceable parts inside.
•
All installation, maintenance and service work should be performed by qualified
service personnel.
The UPS contains its own energy source (battery).
•
The field–wiring terminals may be electrically live, even when the UPS is
disconnected from the utility.
•
Dangerous voltages may be present during battery operation. The battery must
be disconnected during maintenance or service work.
•
This UPS contains potentially hazardous voltages.
•
Be aware that the inverter can restart automatically after the utility voltage is
restored.
Direction 5160944-13-1EN, Revision 2
33