6 IVUS Rev 2 Option

6.1 Wiring Diagram

The connection cables between the IVUS Control Room and Procedures Room components run
in a dedicated under floor conduit (see
A GND wire between the C1 cabinet and the IVUS Rev 2 CPU runs in the underfloor conduit
prepared for the Control Booth cables between Equipment Room and Control Room.
Illustration 6-14:

6.2 IVUS Floor Conduits

A 3 inches and max. 25 m long conduit between Control and Patient Rooms shall be prepared
below the floor for the IVUS Innova interconnection cables.
Chapter 6 Electrical Connections
Section
6.2).