Chapter 6: Installing the Switch in an Equipment Rack

Beginning the Installation

Required Items

Switch
Orientations in
the Equipment
Rack
112
This chapter contains the procedure for installing the switch in a standard
19-inch equipment rack, with the brackets included with the unit.
The following items are required to install the switch in an equipment rack:
Two equipment rack brackets (included with the switch)
Eight M4x6mm bracket screws (included with the switch)
Cross-head screwdriver (not provided)
Four standard equipment rack screws (not provided)
Figure 67 identifies the holes for the standard brackets on the
x950-28XSQ and x950-28XTQm switches.
Holes for
Standard Brackets
Figure 67. Holes for the Equipment Rack Brackets on the x950-28XSQ
Figure 68 identifies the holes for the equipment rack brackets on the
x950-52XSQ and x950-52XTQm switches.
Holes for Equipment
Rack Brackets
Figure 68. Holes for the Equipment Rack Brackets on the x950-52XSQ
and x950-28XTQm Switches
and x950-52XTQm Switches
Holes for
Standard Brackets
Holes for Equipment
Rack Brackets