Alpha ESS SMILE5 Installation, Operation & Maintenance Manual page 9

Energy storage system
Table of Contents

Advertisement

13
Figure 14 Battery power cable installation diagram
Step 4
Close the battery front cover and connect the power cable at the top, which are
included in the parts list of SMILE5-BAT
Figure 15 Assemble Battery Mounting Panel
Step 5 Assemble the battery mounting panel on the battery.
INTRODUCTION
INTRODUCTION
Step 6
depth of about 70mm in the wall for subsequent fixation of the mounting plates.
M5*10 Screws
Step 7
gaskets.
Debris Baffle, drill φ8, depth about 70 mm
Figure 16 Battery Installation - Drill Holes
Position the battery parallel to the wall and use a Φ8mm drill to drill holes at a
NOTE: Place a cover (paper, foil, etc.) over the battery while drilling into the
wall to protect it from dust. In addition, at the place of installation, the slope
of the ground on a horizontal plane may not exceed 3°
φ8*60
Figure 17 Battery Installation – Mounting on the Wall
Remove the debris baffle and secure the battery to the wall with screws and
14
M6 Gasket

Advertisement

Table of Contents
loading

Table of Contents