Wiring plan, connecting
the voltage and current
inputs to power network.
The terminal "k" of CT and
terminal "v" of VT you have
to connecting to earth!
Checking the
connections
18
5.4. Connecting the measuring inputs trough
transformer to power network. Three phase
measurement with neutral conductor. (3 phase, 4 wire, 3
measuring)
The following figure shows the wiring plan, connecting the
instrument to medium voltage power network with neutral
conductor.
1. Loosen terminal screws.
2. Insert the wire ends into the open terminals according to
the wiring plan.
3. Screw the terminal in.
4. Check the hold of the wires in terminals by pulling on
them firmly.
Check if the cables are connected properly (have you
connected all the cables, have you connected to the right
place, do not the cable-ends touch each other).
PQRM5300 33 Ux Ix xx xx (PS)
20201120-V1