6 Commissioning/Start-up/Shutdown
The pump (set) is removed from the pipe and stored
ü All safety regulations are observed.
1. Clean the pump set.
2. Spray-coat the inside wall of the pump casing and, in particular, the impeller
clearance areas with a preservative.

6.4 Returning to service

For returning the pump set to service, observe the instructions on commissioning/
start-up. (ð Section 6.1, Page 42)
Refer to and comply with the operating limits.
For returning the pump set to service after storage also follow the instructions for
maintenance/inspection.
WARNING
Failure to re-install or re-activate protective devices
Risk of injury from moving parts or escaping fluid!
▷ As soon as the work is completed, properly re-install and re-activate any safety-
relevant devices and protective devices.
NOTE
On pumps/pump sets older than 5 years we recommend replacing all elastomer
seals.