UPS5000-A-(200 kVA-800 kVA)
User Manual

3.1.6 Unpacking (300K-FT, 400K, 500K, 600K, 800K)

Context
● Only trained personnel are allowed to move the UPS. Use a pallet truck to
● To prevent the UPS from falling over, secure it to an electric pallet truck using
● To prevent shocks or falls, move the UPS gently. After placing the UPS in the
● If the UPS installation environment is in poor condition and the UPS will be
Procedure
Step 1 Use a pallet truck to transport the UPS to the installation position.
Step 2 Remove the UPS outer packing.
Step 3 Remove the bolts that secure the UPS to the pallet and remove the UPS from the
pallet.
Figure 3-8 Removing the pallet from the UPS
----End
3.1.7 (Optional) Splitting the Power Cabinet and Bypass
Cabinet (300K-FT, 400K, 500K, 600K)
Issue 05 (2020-04-27)
NO TICE
transport the UPS box secured to a wooden support to the installation position.
ropes before moving it.
installation position, unpack it with care to prevent scratches. Keep the UPS
steady during unpacking.
stored for a long time after it is unpacked, wrap the UPS with the original
plastic coat to prevent dust.