3.2.2.1 Installing the UPS on the Floor
Context
● Ensure that the installation floor is flat.
● The marking-off template is delivered with the UPS.
Procedure
Step 1 Determine the cabinet installation positions on the ground based on holes in the
marking-off template for ground installation.
Figure 3-23 Hole dimensions (300K-FT, 400K, 500K, unit: mm)
Issue 05 (2020-04-27)
NO TICE
NO TE
● A: mounting holes on the channel steel
● B: mounting holes on the floor
Copyright © Huawei Digital Power Technologies Co., Ltd.