Figure 41. Loosening captive thumbscrews
Step 12. Unfold and install the other side of the water loop as shown.
Figure 42. Unfolding water loop
Step 13. Ensure the processors are secured properly.
1.
Rotate anti-tilt wire bails (16x anti-tilt wire bails for two nodes) outwards to the locked
position.
2.
Fully tighten all Torx T30 captive screws (16x Torx T30 captive screws for two nodes) on
cold plates in the installation sequence shown on the cold plate label (with a torque
screwdriver set to the proper torque).
Note: For reference, the torque required for the screws to be fully tightened/removed is 0.9-
1.3 newton-meters, 8-12 inch-pounds.
.
Chapter 5
Hardware replacement procedures
65