8.2 Installing Cables for the Rack Mounted Fire
Extinguishing System
Step 1 Take out the reserved cables and install them to the rack mounted fire
extinguishing system.
Ensure that the cables are correctly installed. If a fire occurs when cables are not
connected or incorrectly connected, the ESS cannot actively extinguish the fire.
Ensure that the cables are correctly installed. If a fire occurs when cables are not
connected or incorrectly connected, the ESS cannot actively extinguish the fire.
Figure 8-1 Connecting cables
----End

8.3 Installing Battery Pack Cables

Step 1 Install copper bars for battery packs, and connect the battery rack general output
power cable and black start cable.