● Slowly push or move battery packs to prevent damage and collision.
● To prevent battery packs from falling off, start the pallet truck or forklift after
● Before installation, ensure that battery packs are stored indoors and that other
● Before installation, check the status of the battery packs. Do not use the
● Install battery packs within 24 hours after unpacking. If the battery packs
● Do not install battery packs on rainy, snowy, or foggy days. Otherwise, the
Procedure
Step 1 Remove the column in the middle.
Figure 7-13 Removing the column
Issue 02 (2023-02-28)
CA UTION
confirming that battery packs are securely bound.
NO TICE
storage requirements specified in the user manual are met.
battery packs if the packing cases are exposed to rain, damaged, or deformed,
or if the battery packs leak or fall.
cannot be installed in time, place them in a dry indoor environment without
corrosive gases. Power on the ESS within 24 hours after installation. The
process from unpacking battery packs to powering on the system must be
completed within 72 hours.
battery packs may be eroded by water vapor or rain.