The actually delivered accessories depend on the respective switchgear version and the purchase order. For
detailed information about the actually delivered accessories, please refer to the packing lists.
5.10 Tools
Items required for correct installation:
•
These instructions
•
Measuring sheet of the base frame
•
Lifting truck
•
Several roller pads (reinforced rollers)
•
Several strong boards
•
Rope or chain with transport shackles
•
Reinforcing bars, roller crowbars
•
Torque wrench 8 to 20 Nm, 20 to 70 Nm
•
Electrical or pneumatic screwdriver with a torque of 110 Nm
for hexagon head bolts M16
•
Shims 0.5 mm to 1 mm
•
Phase tape (L1, L2, L3, gn / ye)
•
Plumb bob, nylon thread (kite string or similar)
•
Wire brush, copper sponge
•
Soft, lint-free cloths
•
Brush, cleaning cloth
•
Household cleaner
•
WD-40 waterproof spray oil
Also useful tools:
•
Building site distribution board for 400/230 V AC (50/60 Hz)
•
Extensions for 230 V AC (50/60 Hz)
•
Hydraulic jack (2 to 3 t for vertical and horizontal stroke)
•
Sling ropes
•
Transport rollers
•
Various pieces of squared timber
•
Step-ladders
•
Work bench with vice
•
1/2" and 3/8" ratchet spanners with various extensions
•
Nuts for M8, M10, M12, M16 and M20
•
Ring spanners size 8, 10, 12, 16 and 20
•
Open end spanner size 19
•
Hexagon socket head key size 6
•
Various slotted-head or Torx screwdrivers
•
Side cutter
•
Water pump pliers
•
Various crimping pliers, stripping pliers, flat nose pliers, universal pliers, pointed pliers, etc.
•
Water level
•
Guide string
•
Scriber
•
Try-square
•
Tape measure
•
Thickness gauge (measure the distance in switch-fuse combination)
•
Vernier caliper
•
Measuring instrument with test probes, measuring cables, clamp-type test probes
•
Continuity tester (beeper)
•
Site illumination
•
Hand lamp
•
Pocket lamp
•
Vacuum cleaner
•
Hammer drill
110-0084.9 / 15
≤
NXAIR /
40 kA
Preparing installation