Closing the connection compartment / connection duct
Preconditions
Feeder earthing switch in CLOSED position
High-voltage door open
Low-voltage connector stowed away
Unit consisting of ventilation duct and vertical partition available. Associated connecting elements
available:
13 bolts M8x20 with contact washers and plain washers size 8 acc. to ISO 7093
7 bolts M8x20 with contact washers
Protection plate and associated bolting material available:
4 nuts M8 with contact washers
Front part of ventilation duct and associated bolting material available:
8 bolts M8x20 with contact washers
Procedure
Place the unit consisting of ventilation duct (1) and vertical partition (2) centrally on the panel
base frame. The vertical partition must point towards the connection compartment.
Push the unit towards the connection compartment as far as it will go.
Fix the unit by screwing the bolts hand-tight:
3
2
1
Fig. 267: Ventilation duct and partition,
Tighten the fixing bolts all around with a tightening torque 25 Nm.
Install the protection plate (5).
Fix the protection plate (5) by screwing the nuts (6) hand-tight.
Tighten the fixing nuts with a tightening torque 25 Nm.
184
13 bolts M8x20 with contact washers and plain washers size 8
acc. to ISO 7093 (3)
7 bolts M8x20 with contact washers (4)
4
seen from center-right
4 nuts M8 with contact washers
NXAIR /
3
Fig. 268: Ventilation duct and partition,
seen from center-left
40 kA
4
110-0084.9 / 15

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents