Unloading and erection

6.1

Transport units and packing

The switchgear is delivered in transport units. These transport units consist of individual panels without
mounted busbar. Accessories are packed separately and included with the switchgear.
Transport packing
Freight and storage
Road and air freight
without intermediate storage
Sea, road and air freight
with intermediate storage
6.2

Unloading

110-0084.9 / 15
INFORMATION
Read and understand these instructions before attempting unloading and erection
works.
Packing type
Panels on pallets and open packings with PE protective foil over the
panels
Panels on pallets in closed crate, with sealed upper and lower
PE protective foil, with desiccant bags, with hermetically sealed
wooden base (max. storage time: 6 months)
DANGER
Transports falling down or over
If incorrectly unloaded, the transport units may fall down and cause injury.
Please ensure that the lifting and transport gear used meets the
requirements as regards construction and load-bearing capacity.
Use appropriate lifting equipment and floor conveyors.
Observe the center of gravity of the transport units.
Secure the transport units against tipping.
Move the transport units slowly and carefully.
Do not move transport units with bodily power.
Do not climb onto the roof of the panels.
Put on personal protective equipment.
NXAIR /
Unloading and erection
40 kA