Installation And Fixing Material Without Additional Earthquake Stabilization - Siemens NXAIR Installation Instructions Manual

Medium-voltage switchgear
Hide thumbs Also See for NXAIR:
Table of Contents

Advertisement

5.12 Installation and fixing material without additional earthquake stabilization

Before installing the individual components, the installation and fixing material required has to be prepared.
Floor fixing versions:
Version with bolted floor fixing
Fig. 7: Bolted floor fixing
(1)
Upper edge of finished floor
Floor fixing plate (holder for profiles at a
distance ≥ 1200 mm), Fig. 10 "Side view of the fixing
(2)
plate"
(3)
C-profile CB 50 x 30 x 3, EN 10025, S235JR
Hook-head bolt M16x35-4.6-galvanized
(4)
Washer ISO 7094 - 16 - 100 HV
Hexagon nut ISO 4032 – M16 – 8
(5)
Base frame of panel
(6)
Min. 50 mm
110-0084.9 / 15
NOTICE
Damages due to corrosion
Welded seams are susceptible to corrosion.
After welding, protect the welded seams professionally against corrosion.
Foundation
Double floor
NXAIR /
Bolted
floor fixing
possible
possible
(7)
Min. 90 mm
(8)
80 mm
(9)
Raw floor
Expansion dowel with hexagon
(10)
head bolt and washer: FAN 12/10
(11)
Floor finish
──
──
40 kA
Preparing installation
Welded
floor fixing
possible
not possible
19