Version with bolted floor fixing
Fig. 13: Bolted floor fixing
(1)
Upper edge of finished floor
(2)
Base frame of panel
(3)
Thread for bolt M12 in the U-profiles of the base frame
(4)
U-profile U60, DIN 1026
Floor fixing plate (holder for profiles at a
distance ≥ 1200 mm), Fig. 14 "Fig. 14: Side view of the
(5)
fixing plate"
(6)
Min. 55 mm
Floor fixing plate
110-0084.9 / 15
NOTICE
Damages due to corrosion
Welded seams are susceptible to corrosion.
After welding, protect the welded seams professionally against corrosion.
NXAIR /
(7)
Min. 90 mm
(8)
80 mm
(9)
Raw floor
Expansion dowel with hexagon
(10)
head bolt and washer, FAN 12/10
(11) Floor finish
──
──