Checking Assembly Work; Correcting Circuit Diagrams; Installation Report - Siemens NXAIR Installation Instructions Manual

Medium-voltage switchgear
Hide thumbs Also See for NXAIR:
Table of Contents

Advertisement

Final assembly work

12.14 Checking assembly work

12.15 Correcting circuit diagrams

Note any modifications in the supplied circuit documentation, which may have been made
during installation or commissioning, in the associated documents.
Send the corrected documentation to the regional Siemens representative, so that the
modifications can be included.

12.16 Installation report

After erecting the switchgear, fill in the Installation Report according to chapter 17 and send it to the address
given in the Installation Report.
204
INFORMATION
Check all assembly work executed in the freely accessible areas of the
switchgear. This also includes areas inside non-bolted compartments:
Switching-device compartment
Low-voltage compartment
If it cannot be determined without any doubt that the assembly work in the
not freely accessible areas has been executed properly, make these areas
accessible and check as well:
At covered points of the external enclosure
In the busbar compartment
In the pressure relief duct
In the connection compartment
NXAIR /
40 kA
110-0084.9 / 15