I N S TA L L AT I O N

4 .3 .3 Tower Installation

4.3.3-1-1:
The UPS module is shipped with two sets of feet
Step 1
and 2 short extensions that can be used to tower
4.3.3-1-2:
install the UPS module in 3U. Battery pack is
Step 2
shipped with 4 long extensions that can be used
4.3.3-1-3:
to install UPS module and one battery pack in 6U.
Step 3
4.3.3-2-1:
Step 1
4 .3 .3-1 Install UPS module in 3U
4.3.3-2-2:
Assemble two feet and short extension as one
Step 2
tower stand shown in step 1. Align the two stands
4.3.3-2-3:
approximately 35cm/1.38inch apart in step 2. Then,
Step 3
put UPS module in the stands as shown in step 3.
step 1.
4.3.3-1-1
step 2.
4.3.2-1-2
4 .3 .3-2 Install UPS module and one battery pack in 6U
Assemble two feet and two long extensions as one
tower stand shown in step 1. Align the two stands
approximately 35cm/1.38inch apart in step 2.
Then, put UPS module and battery pack in
the stands as shown in step 3
step 1.
4.3.3-2-1
step 2.
4.3.2-2-2
step 3.
35CM
4.3.2-1-3
step 3.
35CM
4.3.2-2-3