3.2 Site planning and positioning

WARNING!
• Make sure the mains supply and the
total load demand are within UPS
specifications
• The UPS must be powered from a
single-phase grounded wall outlet,
protected by overcurrent devices
according to local wiring rules
• The plug on the power supply cord is
intended to serve as the disconnect
device, the mains socket outlet that
supplies the UPS shall be installed near
the UPS and shall be easily accessible
• After removing covers over battery
terminal, store them safely for future
need. Remove such covers only if it is
intended to attach a connector to a
terminal

3.2.1 Connecting battery

To ensure a long service life, install the unit in a
position where any danger to the UPS is minimized:
Install the UPS indoors.
Leave enough space on each side of the
cabinet to allow cooling airflow and ensure
that the circulation of air to the ventilation
slits is not obstructed.
Avoid excessively high temperatures and
excessive moisture.
Make sure that the surface is solid and flat.

3.2.2 Preparation

For safety consideration, the UPS is shipped out
from factory without connecting battery wires.
Before installing the UPS, please follow below
steps to re-connect battery wires first.
Step 1. Remove front panel. (figure 3.2.1-1)
Step 2. Connect the AC input and
re-connect battery wires. (figure 3.2.1-2)
Step 3. Put the front panel back to the unit.
(figure 3.2.1-3)

3.2.3 Positioning

PowerValue 11 RT G2 can be mounted in a rack
or installed in a standalone configuration.
WARNING!
Water condensation may occur if the UPS is
unpacked in a very low temperature. To avoid
hazards and risk of electric shock, wait until
the UPS is fully dry both inside and outside
before installing / using the UPS.
WARNING!
Handle the UPS carefully to avoid injury
from falling object. Refer to the
technical data sheet for UPS weights.
2
3.2.1-1
Step 1
3.2.1-1
Step 2
1
3.2.1-1
Step 3